Facts & timeline

What is at stake.

Everything on this page is sourced. Where facts are uncertain, we say so.

1968

Opened — brutalist design by G. Wiljouw (Groosman N.V.)

460

Student rooms on the upper floors

~200

Makers in 70+ studios (Urban Resort)

24h

Radion’s licence, since 2015

~6,000

m² of broedplaats space

2027

End of the current temporary-use agreement

Timeline

  1. 1968

    The building opens at Louwesweg 1, Amsterdam, a brutalist block designed by G. Wiljouw of E.F. Groosman N.V. (Rotterdam).

  2. 1984

    ACTA — the Academic Centre for Dentistry Amsterdam (UvA/VU) — moves in.

  3. 2010

    ACTA moves to the Zuidas. Housing corporation de Alliantie buys the building, intending to demolish it and build housing. The crisis makes that unfeasible.

  4. 2012

    Temporary transformation: 460 student rooms on the upper floors, a broedplaats run by Urban Resort on the lower floors. Planned demolition dates (2020, 2023) come and go.

  5. 2014

    Radion opens. In 2015 it receives a 24-hour licence — one of very few in the city.

  6. 2024

    The broedplaats agreement with de Alliantie is extended by 3 years and 4 months, to the end of 2027. The city’s broedplaats policy names ACTA one of three XL broedplaatsen.

  7. 2026

    The new city government (PRO & D66) calls space for makers a “public precondition” and promises clubs a place in new developments.

  8. Oct 2026

    A city planning list (Gemeenteblad 2026, 484436) schedules “Sloterstrip | ACTA: 900 woningen” for construction from June 2029 to November 2032.

  9. 31.12.2027

    The current broedplaats agreement ends. The planning decision for Sloterstrip is expected around this time — which is why we act now.

  10. 2029

    Planned start of construction of 900 homes on the ACTA site — unless ACTA is kept in the plan.

Where things stand

The city has scheduled 900 homes on the ACTA site (2029–2032), but no demolition decision, permit or zoning change has been published yet. The current zoning does not even allow regular housing here — so a new planning decision is needed, and that is where residents, makers and the public get a say. Precedents like OT301 and Bajesdorp were saved because people organised before the decisions were made; De School and Marktkantine were lost when protest started only at the end of the lease. We are early. Let’s keep it that way.

Nitrogen

Demolition needs a permit nobody has yet.

Not a tax — a permit requirement. Since 2022, the nitrogen emitted while demolishing and building counts again, project by project. For 900 homes on the ACTA site that makes the 2029 start date far from certain.

  1. 2 Nov 2022

    The Raad van State strikes down the “building exemption” (Porthos ruling, ECLI:NL:RVS:2022:3159). Nitrogen from the demolition and construction phase must be assessed again for every project.

  2. 18 Dec 2024

    Offsetting new emissions against a site’s current use (“intern salderen”) now counts as a mitigating measure: it requires an appropriate assessment and a nature permit (ECLI:NL:RVS:2024:4923).

  3. 14 Jan 2026

    Pasgeld-West ruling (ECLI:NL:RVS:2026:193): the same applies to zoning plans. The ACTA site needs exactly such a plan change, because the current zoning does not allow regular housing.

  4. 26 Jun 2026

    The cabinet promises a minimum threshold “as soon as possible”, so projects with very little nitrogen deposition no longer need a permit. It is not in force yet.

Our ask: keep ACTA in use until the demolition, building and nature permits are final. Students, makers and Radion should not make way for an empty lot waiting on permits. And publish the nitrogen (AERIUS) calculation for the Sloterstrip plan.

We do not claim how much nitrogen the plan would deposit or on which nature areas — that requires the city’s own AERIUS calculation.